On the 3rd of October at 8:55 pm, an explosion followed by fire of grounding transformer caused a short circuit in one of the autotransformers of substation Foz do Iguaçu - 60 Hz. The disturbance resulted in the complete loss of the transformation and the consequent separation of generation in 60 Hz of Itaipu hydroelectric plant of the Brazilian Interconnected Power System - BIPS. There was action of ERAC in the South / Southeast / Midwest and Acre / Rondônia, which resulted in the shutdown of 3,332 MW of load.
Main actions and measures implemented: