The Action Plan establishes the actions necessary to achieve the strategic objectives of ONS through a portfolio of 49 projects, grouped in nine programs.
The projects developed in the scope of this Action Plan of ONS for the cycle 2009-2012 aimed at:
- Increasing the safety of the energy supply in the BIPS;
- Responding to the challenges resulting from the increased complexity of the BIPS operation, given the diversification of energy sources and its expansion;
- Improving the action of ONS as the manager of the installations network and its performance in the Agents and Institutions in the power sector;
- Implementing the Knowledge Management and Technological Development;
- Incorporating strategic vision to the management of Information Technology, seeking to extend its support to the organization's processes and the rational use of resources;
- Perfecting and consolidating the Management of Personnel;
- Promoting organizational development with a focus on the management of risks, costs and technical and corporate processes; and
- Strengthening the competence and institutional image of ONS.
Amongst the results achieved in 2009, the following should be emphasized:
- the start in the execution of the REGER Project – Electric System Management Grid;
- the continuity in the implementation of the terminal remote units of the SINOCON Project;
- the re-routing of the SIGA Project, with consultants to evaluate the results already achieved and proposing development of the portal into a more modern architecture;
- the evolution of methods, models, processes and tools for the BIPS planning and operation;
- the improvement of models and tools for the electric management of the network;
- the implementation of the ECSs – Safety Control Schemes;
- the investment of ONS in the management of personnel, systems and risks to the continuity of its activities.